The City of Molina de Segura carries out various improvement works in public schools in the municipality for an amount of 265,000 euros, as reported by the Councilor for Education and Municipal Works, Fuensanta Martínez Jiménez.
Of the investment made, 170,000 euros correspond to the Participatory Budgeting item, and 95,000 euros to the investment item in teaching centers of the Municipal Budget, destined to adaptation and improvement works in the public centers of the second cycle of Infant and Primary Education of the municipality.
These are 33 actions, which are the following:
SCHOOL
WORK
one
THE PUREST
Waterproofing of children's canopy cover.
two
THE SIPHON
Interior painted ceilings and vertical parameters.
3
MIÑANO GREGORY
Paint the interior corridors of primary.
4
MASTER FCO.
MTNEZ.
BERNAL
Interior painted ceilings and vertical parameters.
5
SACRED HEART
Interior painted ceilings and vertical gym parameters.
6
FATIMA
Waterproofing of the entire terrace corridor in the skylight area with fiber.
7
FATIMA
Cleaning room reform.
8
TIERNO GALVÁN
Water filtration repair on deck.
9
TIERNO GALVÁN
Make a casket on the covered track with rainwater channeling outwards.
10
TIERNO GALVÁN
Repair of children's games.
eleven
SAN ANTONIO
Roof waterproofing.
12
THE MEDICINES
Conditioning of premises for the school garden workshop.
13
MILL FIELD
Repair of leaks in the sports hall.
14
THE SIPHON
Construction of emergency exit door.
fifteen
MASTER FCO.
MTNEZ.
BERNAL
Renovation of children's toilets.
16
THE PUREST
Pave a small area that connects the access door to the center with the corridor.
17
THE ROMERAL
West courtyard paving next to the health center.
18
VEGA DEL SEGURA
Reform of the changing rooms and toilets of cooks.
19
VEGA DEL SEGURA
Change toilet floors of students and teachers
twenty
SAN MIGUEL
Replacing a porch deck between buildings in the primary courtyard.
twenty-one
SAN MIGUEL
Repair and paint the floor cracks at the end of the covered track.
22
MIÑANO GREGORY
Door replacement.
2. 3
CERVANTES
Adaptation of changing rooms.
24
WALK ROSALES
Fix floor of the upper outdoor terrace and fix grilles and tiles of the outer patio to access the center.
25
VEGA DEL SEGURA
Replace fencing between playground and sports court.
26
FATIMA
Tiling of the assembly hall.
27
CONSOLATION
Painting.
28
MASTER FCO.
MTNEZ.
BERNAL
Remove slope and wax.
30
SAN MIGUEL
Repair the soccer and basketball court.
31
MASTER FCO.
MTNEZ.
BERNAL
Mulberry area paving.
33
TIERNO GALVÁN
Paving with concrete slab in main courtyard.
The Councilor for Education recalled that "all these investments are carried out with the budget of the City of Molina de Segura, since, one more year, the investments made by the Ministry of Education in the Molinense teaching centers are practically non-existent. If the Public schools in Molina de Segura stand out for the quality of their facilities, thanks to the effort made by the City Council, while the Regional Government submits us year after year to an obvious abandonment in terms of educational investments. "